Funding Organization: UNEP/MAP
(United Nations
Environmental Program/Mediterranean Action Plan)
Duration: November
2004 – June 2005
The Mediterranean
Marine Pollution Monitoring and Research Program assists Mediterranean
countries in the formulation and implementation of pollution monitoring
program, including pollution control measures and the drafting of action
plans to reduce and ultimately eliminate pollution from land-based
sources. The Mediterranean marine environment was loaded with the
heaviest pollution. Approximately 80% of it originates from human
activities on land. These activities produce urban, industrial, and
agricultural wastes that are transported by airborne particles and river
run-off carrying nutrients, pathogens, heavy metals, toxic persistent
organic pollutants, oil and radioactive substances. These materials end
up in this regional sea. The Banias-Jebleh area has been confirmed for
the preparation of pre-investment study for domestic and industrial
wastewater management project in Banias.
The Ministry of Housing and
Construction of the Syrian Arab Republic obtained funds from the United
Nations Environment Program/Mediterranean Action Plan for the Banias
Wastewater Project and Rehabilitation of Banias Refinery Industrial
Wastewater Treatment Plant.
The five
main objectives of the study are:
1) Assessment of existing
wastewater system in Banias city and surrounding villages with the aim
to develop a long-term plan for domestic wastewater management;
2) Identification of the
first phase investment program leading to the upgrading and expansion of
the wastewater services and comply with environmental and client
priorities;
3) Conducting a feasibility
study of the priority investments;
4) Assessment of existing
wastewater treatment facility in Banias Oil Refinery with the aim to
improve the industrial wastewater management system; and
5) Identification of priority
measures leading to system improvement and pollution reduction, and
preparing a feasibility study for the industrial wastewater priority
investments for the refinery.
The scope
of the Consultant services will determine the scope and cost of measures
to be taken to reduce wastewater pollution in this described area. These
measures will constitute a project, to be presented to the GEF and other
financing organizations interested in co-financing the investment
project.
The consultancy services for
this project shall be carried out in three Phases:
Phase
A: Preparation of the Inception Report
-
Collect available data,
reports and information
-
Collect and review previous
reports and studies
-
Identify missing data and
information
-
Prepare and submit Final
Inception Report
Phase
B: Develop the Wastewater Management Plan for Banias Area and the Water
Pollution Control Program for the Banias Oil Refinery
Task
B.1. Collection and Review of previously developed plans, systems and
reports
-
Collect previously
identified missing data and information
-
Carryout surveys of the
existing wastewater system and water quality laboratory analysis
-
Review demographic,
socio-economic, and public health studies and reports
-
Review Land-use Master Plan
and asses active rate of development
-
Review design criteria of
the existing wastewater system
-
Assess current water tariff
structure and operation and maintenance costs
-
Review water pollution
abatement policy and discharge standards
-
Assess with the assistance
of the Ministry the existing service area and develop a relevant map
-
Conduct an assessment of
existing wastewater collection and disposal systems
Task B.2. Development of the Domestic Wastewater Management Plan for
Banias Town and Surrounding Villages
-
Conduct a comprehensive
(quick review) of the institutional setup, regulatory framework, and
possibilities of Private Sector Participation
-
Review utility financial
management and administration systems
-
Assess existing O&M system
-
Develop population
projections, water demand, wastewater quantities up to 2025
-
Develop wastewater and storm
water management alternatives
-
Prepare economical and
financial analyses of developed alternatives
-
Prepare and submit Final
Wastewater Management Plan for Banias Town and Surrounding Villages
Task B.3. Assessment of Industrial Wastewater Management Systems in
Banias Oil Refinery and Development of a Water Pollution Abatement
Program
-
Review environmental
management organization
-
Examine regulatory framework
-
Identify plant pollution
characteristics and review existing wastewater collection and
treatment facilities
-
Prepare and submit Final
Water Pollution Management Program Report
Phase
C: Develop the Feasibility Report for Banias Domestic Wastewater and
the Banias Refinery Wastewater Projects
Task
C.1. Feasibility Study for Domestic Wastewater Project
-
Develop environmental impact
assessment study of the proposed project
-
Prepare cost estimates and
economic analysis
-
Prepare project
implementation plan
-
Develop institutional and
organizational measures
-
Prepare and submit Final
Feasibility Study for Domestic Wastewater Report
Task
C.2. Feasibility Study for Industrial Wastewater Project
-
Conduct surveys and
investigations for specific recommended solutions
-
Develop technical project
feasibility
-
Develop preliminary
environmental impact assessment
-
Develop cost estimates and
financial feasibility
-
Institutional analysis and
strengthening
-
Prepare Final Feasibility
Study for Industrial Wastewater Project Report
Next
Previous
|