Pre-investment Study for Banias Wastewater Project and Rehabilitation of Banias Refinery Industrial Wastewater Treatment Plant 

 

Funding Organization: UNEP/MAP (United Nations Environmental Program/Mediterranean Action Plan)

Duration: November 2004 – June 2005

 

The Mediterranean Marine Pollution Monitoring and Research Program assists Mediterranean countries in the formulation and implementation of pollution monitoring program, including pollution control measures and the drafting of action plans to reduce and ultimately eliminate pollution from land-based sources. The Mediterranean marine environment was loaded with the heaviest pollution.  Approximately 80% of it originates from human activities on land.  These activities produce urban, industrial, and agricultural wastes that are transported by airborne particles and river run-off carrying nutrients, pathogens, heavy metals, toxic persistent organic pollutants, oil and radioactive substances.  These materials end up in this regional sea. The Banias-Jebleh area has been confirmed for the preparation of pre-investment study for domestic and industrial wastewater management project in Banias.

The Ministry of Housing and Construction of the Syrian Arab Republic obtained funds from the United Nations Environment Program/Mediterranean Action Plan for the Banias Wastewater Project and Rehabilitation of Banias Refinery Industrial Wastewater Treatment Plant.

The five main objectives of the study are:

1)  Assessment of existing wastewater system in Banias city and surrounding villages with the aim to develop a long-term plan for domestic wastewater management;

2)  Identification of the first phase investment program leading to the upgrading and expansion of the wastewater services and comply with environmental and client priorities;

3)  Conducting a feasibility study of the priority investments;

4)  Assessment of existing wastewater treatment facility in Banias Oil Refinery with the aim to improve the industrial wastewater management system; and

5)  Identification of priority measures leading to system improvement and pollution reduction, and preparing a feasibility study for the industrial wastewater priority investments for the refinery.

The scope of the Consultant services will determine the scope and cost of measures to be taken to reduce wastewater pollution in this described area. These measures will constitute a project, to be presented to the GEF and other financing organizations interested in co-financing the investment project.

The consultancy services for this project shall be carried out in three Phases:

Phase A:  Preparation of the Inception Report

  • Collect available data, reports and information

  • Collect and review previous reports and studies

  • Identify missing data and information

  • Prepare and submit Final Inception Report

Phase B:  Develop the Wastewater Management Plan for Banias Area and the Water Pollution Control Program for the Banias Oil Refinery

Task B.1.  Collection and Review of previously developed plans, systems and reports

  • Collect previously identified missing data and information

  • Carryout surveys of the existing wastewater system and water quality laboratory analysis

  • Review demographic, socio-economic, and public health studies and reports

  • Review Land-use Master Plan and asses active rate of development

  • Review design criteria of the existing wastewater system

  • Assess current water tariff structure and operation and maintenance costs

  • Review water pollution abatement policy and discharge standards

  • Assess with the assistance of the Ministry the existing service area and develop a relevant map

  • Conduct an assessment of existing wastewater collection and disposal systems

Task B.2.  Development of the Domestic Wastewater Management Plan for Banias Town and Surrounding Villages

  • Conduct a comprehensive (quick review) of the institutional setup, regulatory framework, and possibilities of Private Sector Participation

  • Review utility financial management and administration systems

  • Assess existing O&M system

  • Develop population projections, water demand, wastewater quantities up to 2025

  • Develop wastewater and storm water management alternatives

  • Prepare economical and financial analyses of developed alternatives

  • Prepare and submit Final Wastewater Management Plan for Banias Town and Surrounding Villages

        Task B.3.  Assessment of Industrial Wastewater Management Systems in Banias Oil Refinery and Development of a Water Pollution Abatement Program

        

  • Review environmental management organization

  • Examine regulatory framework

  • Identify plant pollution characteristics and review existing wastewater collection and treatment facilities

  • Prepare and submit Final Water Pollution Management Program Report

Phase C:  Develop the Feasibility Report for Banias Domestic Wastewater and the Banias Refinery Wastewater Projects

Task C.1.  Feasibility Study for Domestic Wastewater Project

  • Develop environmental impact assessment study of the proposed project

  • Prepare cost estimates and economic analysis

  • Prepare project implementation plan

  • Develop institutional and organizational measures

  • Prepare and submit Final Feasibility Study for Domestic Wastewater Report

Task C.2.  Feasibility Study for Industrial Wastewater Project

  • Conduct surveys and investigations for specific recommended solutions

  • Develop technical project feasibility

  • Develop preliminary environmental impact assessment

  • Develop cost estimates and financial feasibility

  • Institutional analysis and strengthening

  • Prepare Final Feasibility Study for Industrial Wastewater Project Report